Workers with Great Lakes Construction Co. are preparing for the first concrete pour to repair a portion of the bridge deck ...
Crews allowed media onto the southbound portion of the Daniel Carter Beard Bridge for an up-close look at the repair project.
The Ohio Department of Transportation announced a major step in completing construction on the Daniel Carter Beard Bridge.
Construction workers are nearing a major milestone in the emergency repair works along the Daniel Carter Beard Bridge.
Prep work is underway for the next phase of the I-471 bridge project. The approach to the bridge was damaged beyond repair by ...
Girders are massive steel beams that support the structure of the bridge, according to department of transportation ...
Officials told WCPO 9 News they will begin pouring concrete to form the deck on the southbound side of the bridge soon.
CINCINNATI (WKRC)- Local 12 was given the chance to take a tour of the section under repair of the Daniel Carter Beard Bridge ...
Three of seven steel girders to repair the highway connected to southbound Daniel Carter Beard are here. Four more are coming ...
Repair work has continued this week on the Daniel Carter Beard Bridge, more commonly known as the Big Mac Bridge.
The Ohio Department of Transportation announced that a major step in completing the construction on the Daniel Carter Beard ...
Crews plan to unload the girders on the morning of Jan. 13, according to ODOT. Two more girders are planned to arrive on Jan.